Messaging Migration Assignment
|
Client:
|
International manufacturer serving a global
market for industrial products |
Business Objective:
|
Segregate the messaging infrastructure
from that of the prior parent company
|
Project Description:
|
As part of the sale of the
business by the previous parent company it was required to restructure the
group's messaging system to become independent within the timetable agreed
as part of the sale. |
Metrics:
|
The USA based client had 16
manufacturing units operating in Europe, North and South America, Far East
and Australia. Total number of users of the messaging system was
approximately 1000. |
Results:
|
The project was concluded within a six
week timescale and included the design of a new infrastructure, development
of the
migration methodology and plan, and then management of the rollout process. All without
interruption to the business's use of the messaging system.
|